Camilleri Civil Contractors were awarded the Civil Works package for the re-construction of the Correctional Centres Sewage Treatment Systems. Our scope included pumping out approximately 5million litres of effluent, de-sludging one existing dam then full reconstruction to design.

Bulk Earthworks and blending of unsuitable material of approximately 20,000 cubic meters of material on the two large scale holding dams, including perimeter road construction. The project had our Level One Geo-Technical Engineer’s Supervision.

  • Date Completed: June 2019